Does an ILSM assessment have to be completed for every Survey-related Plan for Improvement?
Any examples are for illustrative purposes only.
An Interim Life Safety Measures (ILSM) assessment must be completed for any Life Safety Code deficiency when it becomes apparent to the organization.
Survey-related Plans for Improvement (SPFIs)^ are developed when the organization cannot correct a deficiency related to NFPA 101-2012 or NFPA 99-2012 within 60 days of the survey event. This SPFI is the basis for requesting a Time Limited Waiver (TLW). The ILSM assessment must be identified in the SPFI entered into the Statement of Conditions (SOC). The validation documentation must clearly demonstrate that the risks identified are being mitigated.
^The Survey Related PFI (SPFI) tab is located on the Statement of Conditions page accessed via the organization's secure extranet site.
An Interim Life Safety Measures (ILSM) assessment must be completed for any Life Safety Code deficiency when it becomes apparent to the organization.
Survey-related Plans for Improvement (SPFIs)^ are developed when the organization cannot correct a deficiency related to NFPA 101-2012 or NFPA 99-2012 within 60 days of the survey event. This SPFI is the basis for requesting a Time Limited Waiver (TLW). The ILSM assessment must be identified in the SPFI entered into the Statement of Conditions (SOC). The validation documentation must clearly demonstrate that the risks identified are being mitigated.
^The Survey Related PFI (SPFI) tab is located on the Statement of Conditions page accessed via the organization's secure extranet site.
Last updated on March 22, 2022
with update notes of: Editorial changes only
First Published Date: April 11, 2016